Phase 1C - Leeville Bridge Construction
June 18, 2009 |
|
|
|
|
|
Contractor has completed approximately 25% of Phase 1A from Port Fourchon to south of Leeville which
is being constructed by "top-down" bridge construction methods. Environmental studies prohibited the use
of haul roads or new canals to build the bridge through the sensitive marshes.
Photos courtesy of James Construction Group.
|
|
|
|
|
|
|